Phase-by-phase schedule
Tile cure and inspection scheduling often extend timelines.
- Demo: 1–3 days
- Rough plumbing and electrical: 3–7 days
- Tile and waterproofing: 5–10 days
- Fixtures and glass: 3–7 days
The days nobody puts on the Pinterest schedule
Waterproofing flood tests, thinset cure, glass measurement after tile, and a city inspection that only happens on Tuesdays are why a “two-week bath” becomes six. If the fan is not ducted outside, that inspection fails even when the tile looks done.
- Glass is measured after walls are tiled, not from the demo-day opening
- A missed plumbing inspection means opening a finished wall
- Special-order vanities can sit in a warehouse while the bath is unusable — order before demo
Living in the house while the only bath is down
If this is the only full bath, budget a temporary toilet or a neighbor arrangement in writing with the GC. A powder room without a shower is not a full-bath substitute for a family. Sequence so one working shower exists whenever you can keep it.
- Ask whether a garden hose shower in the basement is actually in the plan
- Kids and elders change the “we can share a gym shower” math
- Do not start the hall bath the same week the kitchen is also gutted